Bauhaus-Universität Weimar, grounds Geschwister-Scholl-Straße

Product details

Completion:
March 2019
Town/City:
Weimar
Construction time:
April 2018 – March 2019
Client:
Landesamt für Bau und Verkehr
Delivered quantity:
approx. 2,100 m² gravel base course
approx. 1,400 m² water-bound surface course
ca. approx. 1,700 m² paved area of natural stone and concrete pavers
approx. 2,600 m³ earth moving
Supplier:
thomas bau Weimar